03/20/2023 | NOC | Debbie Grosse | APPROVED | | |
|
05/12/2023 | FOOTER BOND | Rinor Krasniqi | DISAPPROVED | FOOTINGS NEAR POOL | 5/11/2023 11:59:57 AM
vb
5/12/2023 12:15:32 PM
Not ready
No print
|
|
05/17/2023 | FOOTER BOND | Rinor Krasniqi | DISAPPROVED - FEE | | 5/16/2023 2:12:21 PM
MT
5/17/2023 12:45:11 PM
Not complete again**
|
|
05/19/2023 | FOOTER BOND | Rinor Krasniqi | APPROVED | | |
|
05/22/2023 | FOOTER/FOUNDATION | Joseph Robinson | DISAPPROVED | 3' X 3' X 1'8'' | 5/22/2023 2:28:12 PM
No permit package.
Dirt touching steel in all footers.
|
|
05/24/2023 | FOOTER/FOUNDATION | Joseph Robinson | APPROVED | | |
|
06/06/2023 | COLUMN BOND | Joe Nieves | DISAPPROVED | COLUMNS NEAR POOL | 6/5/2023 1:52:23 PM
VB
6/6/2023 6:57:54 AM
Inspector EL18 changed the inspection assignment from EL18 to EL12
6/6/2023 10:43:29 AM
The Column Shall Be Bonded With A [ Listed And Labeled Wire Lug Suitable For The Environment] .
NEC 110.3 (B)
|
|
06/06/2023 | FRAMING | Joseph Robinson | APPROVED | | 6/5/2023 1:50:50 PM
VB
|
|
06/09/2023 | COLUMN BOND | Rinor Krasniqi | DISAPPROVED - FEE | | 6/8/2023 2:15:28 PM
MT
6/9/2023 10:41:20 AM
Listed connector for direct burial termination make sure there's no paint where it is attached with a minimum 10-32 screw suitable for the environment recommending "stainless steel"
|
|
06/13/2023 | COLUMN BOND | Rinor Krasniqi | APPROVED | | 6/12/2023 12:20:15 PM
vb
|
|
06/14/2023 | FINAL** | Alejandro Corrales | DISAPPROVED | RE-FEE $$ DUE | 6/13/2023 3:44:28 PM
an
6/14/2023 5:13:20 PM
Pergola incomplete. Louvers not installed and footers are exposed.
|
|
06/26/2023 | FINAL** | Joseph Robinson | DISAPPROVED | RE-FEE $$ DUE | 6/23/2023 1:07:23 PM
an
6/26/2023 2:36:24 PM
Fees must be paid before final inspection.
|
|
06/28/2023 | FINAL** | Anthony Crisanti | APPROVED | | 6/27/2023 12:18:52 PM
ST
|
|