12/14/2022 | NOC | Juan Soto | APPROVED | | |
|
04/10/2023 | SOLAR PANEL ATTACH | Joseph Robinson | DISAPPROVED | | 4/6/2023 9:30:04 AM
JS
4/10/2023 12:47:02 PM
No permit package posted.
No ladder.
|
|
04/10/2023 | ELECTRIC ROUGH | Joe Nieves | PARTIAL APPROVAL | REQUESTING FINAL | 4/6/2023 9:30:29 AM
JS
4/10/2023 1:24:29 PM
Approved Plan And Permit Required For Rough Inspection/ FBC-BCA 107.3.1
|
|
04/11/2023 | ELECTRIC ROUGH | Pedro Vieira | CANCELLED BY PERMITE | | 4/10/2023 3:12:15 PM
ST
4/11/2023 12:40:58 PM
No access
No plans on site
Contractor not on site
No access to roof
|
|
04/11/2023 | SOLAR PANEL ATTACH | Joseph Robinson | CANCELLED BY PERMITE | | 4/10/2023 3:12:59 PM
ST
|
|
04/12/2023 | ELECTRIC ROUGH | Joe Nieves | PARTIAL APPROVAL | | 4/12/2023 12:35:33 PM
Partial Electric Rough Approved/Pending Change Of Plan/Pending Installation Of Correct 40 Amp Fuses.
|
|
04/12/2023 | SOLAR PANEL ATTACH | Will Jorge | DISAPPROVED | | 4/12/2023 4:06:40 PM
installation system not per plan, rails used, not per plan
|
|
06/09/2023 | ELECTRIC ROUGH | Joe Nieves | APPROVED | No Approved Plans | 6/8/2023 10:47:29 AM
ST
6/9/2023 7:02:05 AM
Inspector EL18 changed the inspection assignment from EL18 to EL12
|
|
06/13/2023 | SOLAR PANEL ATTACH | Alejandro Corrales | DISAPPROVED | No Approved Plans | 6/12/2023 12:19:18 PM
vb
6/13/2023 3:02:23 PM
1) All rooftop penetrations (solar stack pedestals) must be sealed with a cementitious or impermeable material. Open cell spray foam was used around penetrations but this will not repel water. Seal around broken tiles and solar stack pedestals
Panel quantity, location and installation is ok.
|
|
06/22/2023 | PE CERTIFICATION | Wyatt T. Haygood | APPROVED | | |
|
06/22/2023 | SOLAR PANEL ATTACH | Will Jorge | APPROVED | | 6/21/2023 11:00:02 AM
ST
|
|
06/23/2023 | ELECTRIC FINAL** | Rinor Krasniqi | DISAPPROVED | No Approved Plans | 6/23/2023 10:39:37 AM
Bonding screw may only be used to bond the can to the grounding conductor, and not to bond the grounding conductor, and the grounded conductor
Wire bites improperly installed, live parts exposed
110.3
|
|
06/27/2023 | ELECTRIC FINAL** | Rinor Krasniqi | DISAPPROVED | | 6/26/2023 11:05:51 AM
ST
6/27/2023 4:04:23 PM
Incomplete, wires under panel #3 from the right touching tile
|
|
06/30/2023 | ELECTRIC FINAL** | Joe Nieves | APPROVED | | 6/29/2023 9:37:57 AM
ST
|
|