04/08/2021 | NOC | Debbie Grosse | APPROVED | | |
|
04/16/2021 | FRAMING | Will Jorge | DISAPPROVED | | 4/15/2021 7:49:50 AM
JS
4/16/2021 1:55:50 PM
no work ready for inspection, no inspection bldg. 9
|
|
04/13/2021 | FRAMING | Tony Willson | PARTIAL APPROVAL | Building #7 | 4/2/2021 9:51:02 AM
Based on letter from Complete Property Services dated Jan. 22, 2021 the anticipated total value of repairs is 200,000.00 dollars.
The anticipated replacement is approximately 35 columns.
The Job Value stated on Permit application is 3,500.oo per column when located.
There will be approximately 106 inspections required for this permit due to there will be a minimum of three inspections per column location with a final inspection required to close out the permit.
4/12/2021 3:08:59 PM
ST
5/4/2021 4:51:19 PM
Building #7 - (4) Balconies @ Front (2) Balconies @ Rear (First Floor Only)
|
|
04/20/2021 | WALL SHEATHING | Tony Willson | PARTIAL APPROVAL | BUILDING #7 | 4/2/2021 9:51:14 AM
Based on letter from Complete Property Services dated Jan. 22, 2021 the anticipated total value of repairs is 200,000.00 dollars.
The anticipated replacement is approximately 35 columns.
The Job Value stated on Permit application is 3,500.oo per column when located.
There will be approximately 106 inspections required for this permit due to there will be a minimum of three inspections per column location with a final inspection required to close out the permit.
4/19/2021 3:57:42 PM
VB
5/4/2021 5:00:58 PM
Bldg. #7 - (4) Balconies @ Front (2) Balconies @ Rear (First Floor Only)
|
|
04/20/2021 | FRAMING | Tony Willson | PARTIAL APPROVAL | BUILDING #9 | 4/19/2021 3:51:04 PM
VB
5/4/2021 4:45:25 PM
Bldg. #9 - (3) Balconies @ Front (First Floor Only)
|
|
04/21/2021 | FRAMING | Tony Willson | PARTIAL APPROVAL | BUILDING #10 & #11 | 4/20/2021 4:08:19 PM
JS
5/4/2021 5:09:31 PM
Bldg. #10 - (4) Balconies @ Front (1) Balcony @ Rear (First Floor Only)
Bldg. #11 - (3) Balconies @ Front (First Floor Only) (1) Balcony @ Rear F.F
|
|
04/28/2021 | WALL SHEATHING | Tony Willson | PARTIAL APPROVAL | Bldg.s #9, #10, #11 | 4/27/2021 3:25:06 PM
th
5/4/2021 5:13:23 PM
Bldg.s #9 - (3) Balconies @ Front (First Floor Only)
Bldg. #10 - (4) Balconies @ Front (1) Balcony @ Rear (First Floor Only)
Bldg. #11 - (3) Balconies @ Front (1) Balcony @ Rear (First Floor Only)
|
|
04/30/2021 | WIRE LATH | Wyatt T. Haygood | DISAPPROVED | bldg #7 | 4/2/2021 9:51:36 AM
Based on letter from Complete Property Services dated Jan. 22, 2021 the anticipated total value of repairs is 200,000.00 dollars.
The anticipated replacement is approximately 35 columns.
The Job Value stated on Permit application is 3,500.oo per column when located.
There will be approximately 106 inspections required for this permit due to there will be a minimum of three inspections per column location with a final inspection required to close out the permit.
4/29/2021 10:02:03 AM
ST
4/30/2021 4:39:28 PM
Wire Lath not complete and ready for inspection.
|
|
05/04/2021 | WIRE LATH | Tony Willson | PARTIAL APPROVAL | BLDG #7 & #9 | 5/3/2021 8:09:00 AM
ST
5/4/2021 4:58:25 PM
Bldg. #7 - (4) Front Balconies (2) Rear Balconies (First Floor Only)
Bldg. #9 - (3) Front Balconies (First Floor Only)
|
|
05/17/2021 | WIRE LATH | Tony Willson | PARTIAL APPROVAL | bldg 10 | 5/14/2021 12:25:37 PM
JS
5/17/2021 4:15:36 PM
Bldg. #10
|
|
05/17/2021 | FRAMING | Tony Willson | PARTIAL APPROVAL | bldg #4 | 5/13/2021 1:07:40 PM
ST
5/17/2021 4:15:39 PM
Bldg. #3 & #4
|
|
05/25/2021 | WALL SHEATHING | Tony Willson | PARTIAL APPROVAL | BLDG #2,3,4,5 | 5/25/2021 3:21:29 PM
Buildings #2, #3, #4, #5 wall sheathing approved.
|
|
06/01/2021 | WIRE LATH | Tony Willson | PARTIAL APPROVAL | Bldg 6 | 5/17/2021 4:29:11 PM
VB
5/26/2021 3:14:50 PM
th Bldg#6
6/1/2021 3:02:26 PM
Building #6 Lath Complete.
|
|
06/02/2021 | WIRE LATH | Tony Willson | PARTIAL APPROVAL | BLDG 4 | 6/1/2021 3:18:56 PM
JS
6/2/2021 2:28:05 PM
Building #4 Wire Lath Approved.
|
|
06/03/2021 | WIRE LATH | Tony Willson | DISAPPROVED | Bldg #3 | 6/2/2021 3:48:29 PM
TH BLDG #3
6/3/2021 3:25:39 PM
Work Incomplete. FBC 110.9.1
|
|
06/08/2021 | WIRE LATH | Tony Willson | PARTIAL APPROVAL | BLDG 3 | 6/7/2021 10:09:14 AM
VB
6/8/2021 4:50:48 PM
Building #3 Wire Lath Completed
|
|
06/08/2021 | WIRE LATH | Tony Willson | PARTIAL APPROVAL | BUILDING 2 | 6/8/2021 4:51:31 PM
Building #2 Wire Lath Completed.
|
|
06/11/2021 | WIRE LATH | Wyatt T. Haygood | PARTIAL APPROVAL | BLDG 5 | 6/9/2021 12:28:22 PM
JS
6/11/2021 2:32:25 PM
Bld # 5 wire lath approved.
|
|
05/19/2021 | WALL SHEATHING | Tony Willson | PARTIAL APPROVAL | BLDG 6 | 5/17/2021 4:28:52 PM
VB
5/18/2021 4:42:54 PM
Building #6
5/19/2021 4:31:30 PM
Building #6
|
|
05/19/2021 | WIRE LATH | Tony Willson | PARTIAL APPROVAL | BLDG 11 | 5/18/2021 3:25:54 PM
VB
5/19/2021 4:31:25 PM
Building #11
|
|
05/18/2021 | FRAMING | Tony Willson | PARTIAL APPROVAL | BLDG 5 | 5/18/2021 4:42:51 PM
Building #5
|
|
05/19/2021 | FRAMING | Tony Willson | PARTIAL APPROVAL | BLDG 2 | 5/18/2021 3:25:16 PM
VB
5/19/2021 4:31:27 PM
Building #2
|
|
06/29/2021 | FRAMING | Tony Willson | APPROVED | BLDG's 2 thru 11 | |
|
06/24/2021 | WALL SHEATHING | Tony Willson | APPROVED | BLDG's 2 thru 11 | |
|
06/24/2021 | WIRE LATH | Tony Willson | APPROVED | BLDG's 2 thru 11 | |
|
07/08/2021 | FINAL** | Tony Willson | PARTIAL APPROVAL | bldg 2 thru 11 | 6/18/2021 1:21:48 PM
TH
6/25/2021 12:07:25 PM
customer changed from 6/29/21 to 7/1/21 Justin morrow 954 842-62332
7/6/2021 2:49:40 PM
Not Ready.
BLDG's #2 & #3 Completed.
7/7/2021 3:18:29 PM
Not Ready.
7/8/2021 2:10:09 PM
BLDG's #4 & #5 Completed.
|
|
07/12/2021 | FINAL** | Tony Willson | PARTIAL APPROVAL | | 7/9/2021 2:51:59 PM
th
7/12/2021 3:18:12 PM
BLDG's #4, #5, #6, #7 Are approved.
|
|
07/13/2021 | FINAL** | Tony Willson | APPROVED | | 7/13/2021 5:04:22 PM
BLDG's #2 thru #11 Completed
|
|