10/20/2021 | NOC | Stephanie Taylor | APPROVED | | |
|
10/21/2021 | SLAB | Joseph Robinson | APPROVED | TOPPER SLAB | 10/20/2021 12:22:53 PM
ST
|
|
03/08/2022 | WIND/DOOR BUCK | Will Jorge | APPROVED | | 3/7/2022 9:06:20 AM
ST
3/8/2022 4:16:08 PM
fin mounted windows
|
|
03/23/2022 | WALL SHEATHING | Joseph Robinson | APPROVED | | 3/22/2022 4:30:36 PM
MT
|
|
03/23/2022 | WIND/DOOR ATTACHMENT | Joseph Robinson | APPROVED | | 3/22/2022 4:31:07 PM
MT
|
|
03/23/2022 | SIDING/T&G IN PROGR | Joseph Robinson | APPROVED | HARDI PLANK | 3/22/2022 4:30:22 PM
MT
|
|
05/24/2022 | ELECTRIC ROUGH | Dean DiBisceglie | APPROVED | | 5/23/2022 8:58:21 AM
vb
|
|
05/25/2022 | ROUGH DUCT | Dave Chin-Sang | DISAPPROVED | | 5/24/2022 3:27:35 PM
vb
5/25/2022 8:53:27 AM
Not ready. Return transfer duct not installed. Supply drops not to plan. COP required
|
|
06/03/2022 | FRAMING | Will Jorge | APPROVED | GARAGE DOOR INFILL | 6/2/2022 2:46:42 PM
MT
|
|
06/03/2022 | INSULATION | Will Jorge | APPROVED | | 6/2/2022 2:46:58 PM
MT
|
|
06/24/2022 | DRYWALL SCREW | Will Jorge | APPROVED | | 6/23/2022 3:27:15 PM
ST
6/24/2022 11:19:23 AM
minor punch out owner will correct
|
|
07/29/2022 | ROUGH DUCT | Dave Chin-Sang | APPROVED | | 7/28/2022 1:31:42 PM
MT
|
|
07/29/2022 | MECHANICAL FINAL | Dave Chin-Sang | APPROVED | UPDATE COI & CAC | |
|
08/11/2022 | ELECTRIC FINAL | Pedro Vieira | PARTIAL APPROVAL | | 8/10/2022 3:04:10 PM
an
8/11/2022 9:42:21 AM
Plan has to be revised including a new 60 amp sub panel installed in new office.
|
|
08/11/2022 | FINAL** | Joseph Robinson | DISAPPROVED | | 8/10/2022 3:05:02 PM
an
8/11/2022 1:45:04 PM
Not ready for inspection.
|
|
09/02/2022 | ELECTRIC FINAL | David Hayes | APPROVED | FEES TO BE PAID B4 FINAL | 9/1/2022 3:06:34 PM
JS
|
|
09/02/2022 | FINAL** | Will Jorge | APPROVED | FEES TO BE PAID B4 FINAL | 9/1/2022 3:06:50 PM
JS
|
|