08/09/2021 | NOC | Debbie Grosse | APPROVED | | |
|
06/04/2021 | PRODUCT APPROVALS | Bill Tracy | APPROVED | | |
|
08/26/2021 | FOOTER/FOUNDATION | Joseph Robinson | APPROVED | | |
|
09/21/2021 | STRUCT MISC REPAIR | Joseph Robinson | APPROVED | BEAM & COLUMN | 9/20/2021 11:26:19 AM
ST
|
|
10/01/2021 | GROUND ROUGH | Jan Trana | APPROVED | | 9/30/2021 1:15:13 PM
JS
10/1/2021 7:48:39 AM
Inspector ME08 changed the inspection assignment from ME08 to PL09
|
|
10/01/2021 | TOP OUT | Jan Trana | APPROVED | | |
|
10/21/2021 | ELECTRIC ROUGH | Dean DiBisceglie | PARTIAL APPROVAL | PARTIAL | 10/20/2021 9:10:56 AM
ST
|
|
10/06/2021 | SPOT SURVEY | Bill Tracy | APPROVED | | 10/6/2021 12:13:38 PM
ADDITION SPOT - X-ZONE
|
|
12/14/2021 | ELECTRIC DEMO | Dean DiBisceglie | APPROVED | | 12/10/2021 3:18:43 PM
st
|
|
12/16/2021 | ELECTRIC ROUGH | Dean DiBisceglie | APPROVED | | 12/15/2021 7:58:29 AM
wth
|
|
12/16/2021 | LOW VOLTAGE ROUGH | Dean DiBisceglie | APPROVED | | 12/15/2021 8:00:22 AM
wth
|
|
12/16/2021 | STRUCT MISC REPAIR | Wyatt T. Haygood | APPROVED | Steel Beam | 12/15/2021 7:58:11 AM
wth
|
|
12/16/2021 | SLAB | Wyatt T. Haygood | APPROVED | | 12/15/2021 7:58:52 AM
wth
|
|
12/16/2021 | SOIL TERMITE TREAT | Wyatt T. Haygood | APPROVED | | 12/15/2021 7:59:18 AM
wth
|
|
12/16/2021 | TIE BEAM/BOND | Wyatt T. Haygood | APPROVED | | 12/15/2021 7:59:48 AM
wth
|
|
12/16/2021 | WALL SHEATHING | Wyatt T. Haygood | APPROVED | | 12/15/2021 8:02:22 AM
wth
|
|
12/16/2021 | TRUSS | Wyatt T. Haygood | APPROVED | | 12/15/2021 8:01:57 AM
wth
|
|
12/27/2021 | UNIT MASONRY CERT | Wyatt T. Haygood | APPROVED | | |
|
12/28/2021 | FRAMING | Will Jorge | DISAPPROVED | | 12/27/2021 8:21:11 AM
wth
12/28/2021 2:21:00 PM
draft stop and framing incomplete. support framed ceilings every 4'o/c
|
|
12/29/2021 | FRAMING | Will Jorge | PARTIAL APPROVAL | | 12/29/2021 2:18:04 PM
kitchen and dining area, walls and ceiling
|
|
01/03/2022 | INSULATION | Tony Willson | CANCELLED BY PERMITE | | 12/30/2021 11:47:20 AM
ST
1/3/2022 8:12:55 AM
DEAN
|
|
01/03/2022 | WIRE LATH | Tony Willson | APPROVED | | 12/29/2021 11:54:28 AM
ST
|
|
01/04/2022 | INSULATION | Joseph Robinson | DISAPPROVED | | 1/3/2022 2:29:07 PM
ST
1/4/2022 12:06:04 PM
Exterior wall insulation already covered with drywall on second floor.
Second floor bathrooms tiled.
Work covered. Unable to inspect insulation.
Provide pictures of covered work.
|
|
01/05/2022 | INSULATION | Tony Willson | APPROVED | | 1/4/2022 4:35:51 PM
ST
|
|
01/13/2022 | DRYWALL SCREW | Joseph Robinson | DISAPPROVED | | 1/11/2022 2:26:11 PM
MT
1/13/2022 5:23:36 PM
Bathrooms tiled and some walls finished and painted.
Drywall incomplete in some areas.
Work covered.
Work incomplete.
Provide pictures of covered work.
|
|
01/14/2022 | DRYWALL SCREW | Wyatt T. Haygood | CANCELLED BY PERMITE | | 1/14/2022 7:41:44 AM
mt-cx by steven
|
|
01/18/2022 | FRAMING | Wyatt T. Haygood | APPROVED | | 1/18/2022 7:47:23 AM
wth
|
|
01/18/2022 | DRYWALL SCREW | Wyatt T. Haygood | APPROVED | | 1/18/2022 7:48:27 AM
wth
|
|
01/18/2022 | WIND/DOOR BUCK | Wyatt T. Haygood | APPROVED | | 12/16/2021 2:07:25 PM
wth
1/18/2022 7:48:01 AM
wth
|
|
05/04/2022 | LOW VOLTAGE FINAL | Dean DiBisceglie | APPROVED | | 5/3/2022 10:25:42 AM
JS
|
|
05/04/2022 | ELECTRIC FINAL | Dean DiBisceglie | APPROVED | | 5/3/2022 10:25:18 AM
JS
|
|
05/04/2022 | PLUMBING FINAL | Jeremy Hassenplug | DISAPPROVED | | 5/3/2022 10:25:51 AM
JS
5/4/2022 12:29:06 PM
Need to install vents on wall mounted vanities with s-traps.
All shower trims need to be caulked.
Escutcheons need to be installed on all plumbing pipes in vanities.
Toilet in her closet running.
Install sinks in downstairs bathrooms.
|
|
05/04/2022 | WIND/DOOR ATTACHMENT | Alejandro Corrales | PARTIAL APPROVAL | | 12/16/2021 2:07:43 PM
wth
5/4/2022 4:49:07 PM
All openings inspected. Provide photos of all fasteners for the 2 SGDs and adjust the door so the hurricane latches engage properly. All other openings are ok and covers can be installed .
|
|
05/10/2022 | FINAL SURVEY | Wyatt T. Haygood | APPROVED | | |
|
05/24/2022 | PLUMBING FINAL | Jeremy Hassenplug | DISAPPROVED | | 5/23/2022 3:59:18 PM
ST
5/24/2022 1:10:30 PM
Need to caulk shower trim and replace drum trap with self cleaning trap
|
|
05/24/2022 | WIND/DOOR ATTACHMENT | Alejandro Corrales | APPROVED | | 5/23/2022 3:59:35 PM
ST
|
|
06/09/2022 | PLUMBING FINAL | Jeremy Hassenplug | APPROVED | | 6/8/2022 3:29:16 PM
VB
|
|
06/17/2022 | TRUSS PLANS ON FILE | Wyatt T. Haygood | APPROVED | ELEVATOR PERMIT REQ'D | 6/17/2022 5:07:37 PM
Elevator permit inserted into file
|
|
06/23/2022 | FINAL | Joseph Robinson | APPROVED | | |
|
06/23/2022 | ADMIN CHECKLIST** | Victoria Barrios | APPROVED | | |
|