03/31/2022 | NOC | Stephanie Taylor | APPROVED | | |
|
05/11/2022 | GROUND ROUGH | Jeremy Hassenplug | APPROVED | REQUESTING PM | 5/10/2022 12:50:44 PM
JS
|
|
05/16/2022 | SOIL TERMITE TREAT | Wyatt T. Haygood | APPROVED | Footings and Slab repair | 3/22/2022 9:21:38 AM
Footings and Slab repair
|
|
05/17/2022 | CONSULTATION | Wyatt T. Haygood | APPROVED | | 5/17/2022 1:42:33 PM
Spoke to jobsite foreman about general site conditions
|
|
05/18/2022 | ELECTRIC ROUGH | Dean DiBisceglie | APPROVED | | 5/16/2022 3:32:52 PM
wth
|
|
05/18/2022 | ROUGH DUCT | Dave Chin-Sang | DISAPPROVED | | 5/16/2022 3:33:19 PM
wth
5/18/2022 10:54:18 AM
Supply duct for 1st floor pantry not installed.
Duct support shall be 1 1/2" minimum. Tie strap not an approved support
Duct not to plan. Plan shows (1) 6" feeds (2) 4"
Flex duct connection to collar not sealed.
|
|
05/18/2022 | EXHAUST ROUGH | Dave Chin-Sang | DISAPPROVED | | 5/16/2022 3:33:55 PM
wth
5/18/2022 10:54:20 AM
FBC/Residential M1501.1 exhaust fan shall terminate outdoor.
(1) 4" duct not large enough for 2 exhaust fan.
|
|
05/24/2022 | EXHAUST ROUGH | Scott Wiesel | APPROVED | | 5/23/2022 2:50:48 PM
ST
|
|
05/25/2022 | FOOTER/FOUNDATION | Joseph Robinson | APPROVED | Footings and Slab repair | 3/22/2022 9:17:55 AM
Footings and Slab repair
5/24/2022 10:26:39 AM
MT
|
|
06/10/2022 | TOP OUT | Jan Trana | APPROVED | | 6/9/2022 3:01:39 PM
JS
|
|
06/13/2022 | FRAMING | Wyatt T. Haygood | APPROVED | for Wyatt | 6/10/2022 2:36:12 PM
wth
|
|
06/13/2022 | TUB ROUGH-IN | Scott Wiesel | APPROVED | | 6/10/2022 2:35:43 PM
wth
|
|
06/13/2022 | SHOWER PAN | Scott Wiesel | APPROVED | | 6/10/2022 2:34:58 PM
wth
|
|
06/13/2022 | ROUGH DUCT | Scott Wiesel | APPROVED | | 6/10/2022 2:34:19 PM
wth
|
|
06/13/2022 | TIE BEAM/BOND | Wyatt T. Haygood | APPROVED | Window opening infill | 3/22/2022 9:22:32 AM
Window opening infill
|
|
06/13/2022 | WIND/DOOR BUCK | Wyatt T. Haygood | APPROVED | | |
|
06/14/2022 | COLUMN | Wyatt T. Haygood | APPROVED | | 6/13/2022 2:31:58 PM
VB
|
|
06/16/2022 | DRYWALL SCREW | Will Jorge | APPROVED | | 6/15/2022 5:27:02 PM
MT
|
|
06/23/2022 | DRYWALL SCREW | Joseph Robinson | APPROVED | FOR SHOWER | |
|
12/07/2022 | INSULATION | Joseph Robinson | APPROVED | | 12/6/2022 10:42:07 AM
MT
|
|
02/15/2023 | MECHANICAL FINAL | Dave Chin-Sang | APPROVED | | 2/14/2023 1:51:04 PM
CJ
|
|
02/16/2023 | ELECTRIC FINAL | Rinor Krasniqi | DISAPPROVED | | 2/14/2023 1:51:58 PM
CJ
2/16/2023 11:07:00 AM
Not complete
408.4 label panel
404.9 flush faceplate switch
406.5 flush receptacle uncut faceplate
210.8 gfci kitchen
NEED DOCUMENTS FOR TOILET
NEED SCOPE OF WORK
NOT COMPLETE LIST
|
|
02/28/2023 | ELECTRIC FINAL | Rinor Krasniqi | APPROVED | | 2/27/2023 1:56:19 PM
ST
2/28/2023 11:40:05 AM
Inspector EL18 changed the inspection assignment from EL18 to EL12
2/28/2023 12:05:27 PM
Inspector EL12 changed the inspection assignment from EL12 to EL18
2/28/2023 12:15:24 PM
I misunderstood scope of work
Bathroom issues were addressed
|
|
03/16/2023 | PLUMBING FINAL | Jeremy Hassenplug | APPROVED | | 3/15/2023 3:33:06 PM
wth
|
|
03/24/2023 | FINAL** | Will Jorge | APPROVED | | 3/23/2023 9:37:11 AM
wth
|
|