Permit No. BLDG2202-0226 Permit Type   INTERIOR REMODEL Site Address   10432 NW 69 MNR
PARKLAND, FL 33067
Applied   02/25/2022 Applicant  
Approved   03/01/2022 Owner   ROSENBERG,MARC &
Issued   03/24/2022 Contractor   PARADISE REMODELING & DESIGN LLC
Parent Permit No.   Description   BATHROOM RENOVATIONS (3)
  Notes  
 
  Date of Inspection Inspection Type Inspector Result Remarks Notes

 03/24/2022NOCStephanie TaylorAPPROVED

 05/19/2022TOP OUTJeremy HassenplugPARTIAL APPROVAL5/18/2022 9:31:00 AM ST 5/19/2022 11:30:10 AM Cabana and kid's bathrooms top out approved.

 05/20/2022FRAMINGAlejandro CorralesDISAPPROVED5/19/2022 12:32:16 PM MT 5/20/2022 4:09:35 PM Not ready. Hole in wall where shower mixing valve is must be stuccoed. A furring strip was removed and must be reinstalled. Stud to stud spacing must be 16'' max where tile will be installed. Kick plates (protective plates) must be installed over plumbing or electrical that passes through a stud or furring strip. Foam the corners of the top track. This is not required for remodeling work but I do recommend it (seal the walls from the attic space)

 05/23/2022TOP OUTJeremy HassenplugPARTIAL APPROVAL5/20/2022 1:17:18 PM JS 5/23/2022 11:48:58 AM Called by mistake

 05/24/2022FRAMINGAlejandro CorralesPARTIAL APPROVAL5/23/2022 11:31:25 AM vb 5/24/2022 2:06:45 PM Framing approved for Kids and cabana bathrooms. Work not started on master bathroom yet. Ok move forward in these 2 bathrooms only.

 05/25/2022DRYWALL SCREWJoseph RobinsonPARTIAL APPROVAL5/24/2022 12:37:50 PM ST 5/25/2022 1:02:04 PM Only 2 bathrooms inspected.

 06/23/2022TOP OUTJan TranaAPPROVED6/22/2022 11:52:42 AM JS

 06/23/2022SHOWER PANJan TranaAPPROVED6/22/2022 11:52:33 AM JS

 06/24/2022FRAMINGAlejandro CorralesAPPROVED6/23/2022 1:33:36 PM JS

 06/24/2022DRYWALL SCREWAlejandro CorralesDISAPPROVED6/23/2022 1:33:54 PM JS 6/24/2022 2:27:33 PM Schedule when master bath drywall is installed

 06/28/2022DRYWALL SCREWJoseph RobinsonAPPROVED6/27/2022 12:36:30 PM VB

 09/13/2022PLUMBING FINALJeremy HassenplugPARTIAL APPROVALSINK REVISION PLANS9/12/2022 9:57:52 AM VB 9/13/2022 1:08:57 PM Need vent in tub bathroom sink

 09/23/2022PLUMBING FINALJeremy HassenplugAPPROVED

 10/13/2022FINAL**Alejandro CorralesAPPROVED10/6/2022 2:49:19 PM ST